Scrum Artefacts: Burndown Chart

As a definition of this chart we can say that the Burndown chart displays the remaining effort for a given period of time.

Sprint Burndown Chart

Teams use the sprint Burndown chart to track the product development effort remaining in a sprint.

General speaking the Burndown chart should consist of:

  • X axis to display working days
  • Y axis to display remaining effort
  • Ideal effort as a guideline
  • Real progress of effort

Organizations use different attributes on the Y axis. All of them have benefits and drawbacks.

Scrum Artefacts: Burnup Chart

A burnup chart, or burnup chart, tracks progress towards a projects completion. In the simplest form of burn up chart there are two lines on the chart:

  1. A total work line (the project scope line)
  2. A work completed line

A burnup chart clearly shows both completed work and project scope. The project will be completed when the lines meet.

The vertical axis is amount of work, and is measured in units customized to your own project. Some common units are number of tasks, estimated hours or story points (in agile project management methodologies). The horizontal axis is time, usually measured in days.

Each day you can see the amount of work completed and the total amount of work. The distance between the two lines is thus the amount of work remaining. When the two lines meet, the project will be complete. This is a powerful measure of how close you are to completion of the project, similar to a burn down chart.